Gawar

Khajuwala Bap Highway

Start date

May 22, 2019

Kms

212.107

Project is for Upgradation to 2 lane with paved shoulder/4 lane of Khajuwala – Poogal section (Design Chainage 0.000 to 30.812) and Poogal – Dantour – Jaggasar – Gokul – Goddu – Ranjeetpura – Charanwala – Naukh – Bap section of NH-911 (Design Chainage 1.430 to 182.725) (Total length 212.107 Km) under Bharatmala Pariyojna in the state of Rajasthan on Hybrid Annuity Mode of NHAI.

The project was awarded on 27th March 2018 and the Concession Agreement was signed on 28th September 2018. The project received Pre-COD on 20th January 2021 and COD achieved on 30th October 2021 and is in operation phase, which will continue till 2036. The project received an early completion bonus for achieving COD four months before its scheduled time.

Scroll to Top